
Message from the Eskom Chief Executive – Jacob Maroga
Power supply interruptions of the scale seen during the reporting year have been unprecedented in South Africa. Meeting an increasing national demand for electricity with a much-diminished reserve margin has undoubtedly been Eskom’s biggest challenge for this past financial year.
The convergence of a diminished reserve margin, increased unplanned generation plant outages as well as coal supply and quality constraints forced Eskom into an undesirable position of having to interrupt the supply of electricity nationally.
Between October 2007 and February 2008, emergency load shedding was implemented. In order to avoid a potential overall nationwide blackout, a national electricity emergency was declared on 24 January 2008.
Since taking office as chief executive on 1 May 2007, my team and I have dedicated a significant amount of leadership time reflecting on the challenges at hand and aligning all the resources of the organisation towards a solution. The fundamental and underlying problem is that the power system has an inadequate reserve margin which is at an all time low of around 8%. This does not compare well to our aspiration of 15%.
Since 1994, the demand for electricity has grown by about 50% on the back of robust economic growth. This welcomed growth has all but exhausted Eskom’s surplus electricity generation capacity. To us at Eskom, this has been one indicator that we watched closely and with a sense of trepidation. Monitoring the diminishing reserve margin has been an integral par t of Eskom’s operations, as it is a proxy for the long-term adequacy of the power system, including the short-term security of supply. In the absence of any investment in new generation capacity, misalignment between the demand and the available supply emerged and therefore the 2007 crunch was inevitable. The Cabinet decision of 2004 marked an important milestone where Eskom could start investing in new generation capacity.
Increasing Eskom’s reserve margin to adequate levels is central to the organisation’s ability to ensure that power supply is not impacted by technical events upstream in the supply chain. A healthy reserve margin is necessary to create a window for planned maintenance and a cushion to manage unplanned maintenance. In this way conventional and inevitable technical problems are absorbed within the system and do not degenerate to a national crisis. This margin is further required to optimise the cost of running the power system. With such an inadequate reserve, Eskom has very little choice but to run all the available power stations irrespective of the cost of running them.
Despite the low reserve margin, Eskom has commenced issuing quotations to potential customers who apply for new connections or upgrades above 100kVA. However, the period that it will take before a customer applying for a connection above 100kVA receives energy will depend on the rate at which space is created on the electrical system and the rate at which applications for new capacity are received.
Eskom is embarking on a very large infrastructure expansion programme which has a board-approved budget of R343 billion up to 2013 and is expected to grow to more than a trillion rand by 2026. Additional power stations and major power lines are being constructed in line with our plan to deliver an additional 16 304MW in generation capacity by 2017. Ultimately, Eskom will double its capacity to about 80 000MW by 2026.
This massive build programme has been designed such that it adequately responds to the challenge of electricity availability and reliability. It has also been aligned with government’s target of 6% GDP growth between 2010 and 2014.
I am pleased to report that the Eskom build programme is on track to deliver the additional infrastructure as planned. We have made excellent progress during the past financial year, and have indeed achieved what we set out to do in this regard. Ankerlig and Gourikwa power stations – the two new open-cycle gas turbine stations located in the Western Cape – were officially opened. The National Energy Regulator of South Africa (Nersa) granted Eskom the licence to build the first new coal-fired power station in more than 20 years.
Hitachi Power Africa was awarded a R20 billion contract for boilers, and Alstom S&E was awarded a R13 billion contract for turbines for Medupi power station. We also awarded contracts worth some R31,5 billion for the “Bravo Project”, a coal-fired power station to be built by 2017 – R18,5 billion to Hitachi Power Africa for boilers and R13 billion to Alstom S&E for turbines.
Work is well underway on the return to service of the three previously mothballed power stations – Camden, Komati, and Grootvlei. The construction of Ingula pumped storage scheme is also progressing well. We are also on track with several of our transmission projects.
For the reporting year, capital expenditure of R24,7 billion was incurred. This was R218 million above the target for the year – a confirmation that the accelerated programme is on track.
I must pay special tribute to the Eskom team for ensuring that this all important programme of building new capacity remains on track notwithstanding all the adversities brought about by an inadequate reserve margin.
Ensuring the security of supply at a time when the power system has an inadequate reserve margin will remain a key challenge for South Africa, the electricity sector, and Eskom. We accept that the load shedding activities of the magnitude seen in recent times have dented South Africa’s confidence in the power system and in Eskom. We have made the commitment to regain public confidence in the system. In this regard, all our work towards re-building trust will be based on open, honest and transparent sharing of information.
For the next five years at least, the South African power system will remain vulnerable given the low reserve margin. Plans are in place, and implementation has been accelerated. We are confident that the activities we are undertaking today – as Eskom, the energy sector, government, and the country at large – will enhance Eskom’s ability to deliver into the future. |