Eskom   Home_pic
 
Home | Site map
Decrease font size   Increase font size   Print this page   E-mail this page
 
 
Profile
Southern Africa grid map
Key facts
Electricity:
from power station to customer
Organisational structure
Executive summary
Vision, values and
strategic objectives
Group five-year review
Downloads
Additional Information
Information Sheets
Keyword search
 
   
 
Business and sustainability performance review  
SECURING CONTINUITY OF SUPPLY  
 
Load shedding – demand exceeds supply | Stabilisation and recovery plan | Generation plant performance  
 
Transmission system performance | Distribution system performance | Primary energy  
   
 
Stabilisation and recovery plan  
   
  Lethabo power station near Vereeniging
  Lethabo power station near Vereeniging.
   
 
 
National response plan

The Department of Minerals and Energy and the Department of Public Enterprises launched a national response plan to the electricity challenge on 25 January 2008.

This plan involves plans to increase generating capacity – Eskom’s build programme, as well as co-generation and a 1 000MW open-cycle gas turbine power station to be built by an independent power producer. On the demand side, the plan includes the medium-term power conservation programme (PCP) and demand-side management programmes.

Eskom stabilisation and recovery plan

Eskom has established a three-phase stabilisation and recovery plan for the next five years. In phase 1, we stabilised the supply of, and demand for, electricity. Phase 2 involves re-establishing an adequate reserve margin by managing demand; and then in phase 3, we plan to establish a sustained load reduction of 3 000MW through the power conservation programme.

The emergency load shedding at the start of 2008 enabled a 4 000MW load reduction by the end of February 2008. This enabled us to reduce generation load losses and to provide for more planned maintenance.

In response to a call for a sustained 10% reduction in demand, key industrial customers are already voluntarily providing 1 200MW in load reduction. Eskom itself achieved a 1 000MW reduction in load losses by stabilising coal supply.

Unfortunately, only limited reductions were forthcoming from other customers by the end of March 2008.

  Solar-powered traffic lights research

 

A research project was initiated in 2007, to evaluate a solarassisted battery back-up energy supply solution for traffic lights. The project was a collaboration between Eskom research and innovation department and the National Energy Efficiency Agency. A pilot site, an eight-robot intersection, was identified in Cape Town, where the official launch took place on 1 October 2007.

The traffic lights at the intersection were retrofitted with energy-efficient LED lights, a monitoring unit, a solar panel and batteries. The pilot site was monitored and measured for three months to determine the success of the technology. The aim of this project was to evaluate and demonstrate the success of a solar-assisted battery solution for this application as an effective means of providing back-up power supply to large traffic intersections during power outages.

  Click here for more about the solar powered traffic lights
 
Implementing the recovery plan

Eskom has established a recovery task team around the supply and demand side of the business, focusing on six major streams: supply-side recovery; power buy-back; demand-side management (DSM); public confidence building and communication; employee morale and engagement; planning, risk and resilience management.

The aim is to re-establish our ability to provide a secure power supply by achieving a sustained reduction of 3 000MW over the next four years. This sustained reduction, together with the new capacity from the build programme, improved coal quality and quantity and plant performance, will enable the reserve margin to recover to about 15% between 2010 and 2012 and should provide sufficient energy to cater for the expected economic growth. We will need further interventions by 2012, when the reserve margin is expected to drop to about 9%.

 
Impact of 3 000MV reduction in demand
 
Supply-side recovery

The supply-side recovery team is working hard to return coal stock to 20 days (refer here) and improve the generation plant reliability and availability, so that the UCLF (unplanned capability loss factor) and OCLF (other capability loss factor) are consistently within the reserve margin allowance (refer here).

Power buy-back and demand-market participation (DMP)

The power buy-back team needs to obtain a 2 000MW to 3 000MW demand reduction from energy-intensive customers (furnace and smelting processes) and marginal producers. This is in the feasibility phase.

The DMP programme allows customers to offer Eskom flexible loads on a year-ahead or day-ahead basis, at a favourable predetermined price. When Eskom is experiencing a load shortage, we can first reduce or cut the load to these DMP customers before having to consider other load shedding options. The programme is approved by Nersa and has prevented load shedding on many occasions over the past year. DMP savings of 67MW were contracted for 2008.

Demand-side management (DSM)

Demand-side management involves the installation of energyefficient and load-shifting technologies to alter the load profile of Eskom. As such it is “hard wiring” savings into the system thereby ensuring a higher level of security of supply in the short to medium term.

There is a need to remove a certain amount of energy, measured in GWh, from the system before 2012, when the supply side options will assist in energy supply. This can be achieved by co-generation, DSM and permanent behaviour change of customers. As a result of this analysis, it is apparent that DSM needs to be accelerated to achieve the required 10 000GWh saving by 2011/12. This requires
3 800MW of energy saving devices to be installed over the next four years. The main focus will be on lighting (residential, commercial and industrial), solar water heaters, smart meters and motor systems.

Mass rollout programmes will involve residential lighting, smart meters and solar water heating. The latter two options will be rolled out in the second half of 2009 and 2010.

In addition to these mass rollout programmes, smaller projects are driven by independent energy services companies (ESCos). These projects yield valuable MWh savings by large industries and corporate customers. 2009 and 2010 will place a large emphasis on energy-saving initiatives, mainly lighting, by using these resources.

DSM implementation has been guided by Nersa, which includes verifiable short-term DSM savings in its multi-year price determination (MYPD) tariff setting process. Verified DSM savings of 650,4MW (which includes DMP contracted savings of 67MW) were achieved for the year against the Eskom target of 400MW (2007: 169,8MW verified against the Eskom target of 213MW). The mass rollout of compact fluorescent lamps (CFLs) in early 2008 contributed 389,9MW to these savings.

Should the DSM initiatives not result in these energy savings, there is an increased risk of load shedding from 2010 until the supply side options are available. The success of the programme to remove 10 000GWh out of the system by 2011/12, will depend on the correct funding levels being available over the next four years, regulatory support to ensure the correct projects can be implemented, as well as to allow flexibility in the implementation to ensure optimum deployment of DSM interventions.

  Click here for more details on DSM initiatives.

 
 
   
 
Stabilisation and recovery plan     Back to top