THE OSD FACILITY (UNIT 1) GEARS UP FOR
INCREASED DEMAND
An increase in demand at Unit 1, the FDA-approved OSD
Facility at the Port Elizabeth site, resulted in the implementation
of capital expenditure projects to unlock capacity in the
constrained manufacturing areas. Unit 1 primarily manufactures
high-volume products for domestic supply as well as products for
Aspen’s international markets. Additional roller compaction,
encapsulation and coating capacity was successfully installed
during the first half of 2009 and has contributed towards doubling
the output in the encapsulation and tablet coating areas. An
investment in two high-speed bottling lines, which commenced
production in April 2009, has increased packing capacity.
Aspen’s continued growth in South Africa and its recent
expansion into international markets has resulted in an
increased requirement for manufacturing capacity for high
volume products. Consequently, a capacity enhancement project
has been initiated at Unit 1 to increase the current granulation
and compression capacity. This project is anticipated to be
completed during 2010.
RATIONALISATION AND OPTIMISATION OF
THE FACILITIES IN
PORT ELIZABETH AND
EAST LONDON
Small and medium volume products for domestic supply,
including solid, liquid and semi-solid dosage forms, are
manufactured at the Heritage Facility in Port Elizabeth. The
East London site has historically been the manufacturer of oral
contraceptives and selected consumer and OTC products.
Owing to Aspen’s growing demand, investment has been
made in capital expenditure projects to upgrade the Heritage
Facility and to extend the manufacturing capability and capacity
at the East London site to include pharmaceutical products.
These infrastructure upgrade projects, extending over three
inter-dependent phases, will also be at enhanced levels
of Good Manufacturing Practice ("GMP") compliance.
In the first phase of this project, the existing warehousing facilities
in Port Elizabeth were expanded and upgraded to accommodate
the growth in volume. This project was completed in 2008.
The second phase encompasses the replacement of the
OSD manufacturing areas at the Heritage Facility. This
new OSD Facility will be referred to as Unit 2. A high-rise
structure, completed in June 2009, was constructed to
house the granulation, fluid-bed drying, compression and
coating areas. An investment has been made in new equipment
and high calibre technical support services for this area. The
implementation of advanced technology and world-class
manufacturing processes is expected to increase and optimise
throughput. Longer production runs, for higher-volume
products, present an opportunity for realising economies of
scale. Operating staff have received the necessary equipment
and process training to empower them to work effectively in
the upgraded environment. Unit 2 commenced commercial
production in September 2009.
The completion of the third phase, for the refurbishment of
Unit 3, will result in a manufacturing area for the production of
lower volume OSD products, a limited range of semi-solids and
liquids and an upgrade of the existing solids packaging areas. Pre-construction
activities in this section commenced in May 2009
and the project is scheduled to be completed in 2010. In the last
year, the packing capacity for patient-ready packs supplied to the
tender market, has already been doubled through investment in
additional equipment.
As a result of Aspen’s strategic focus on pharmaceutical
products, the manufacture of selected fast-moving consumer
goods such as aerosols, personal care and dental products
has been transferred from the East London site to accredited
third-party manufacturers. The resultant capacity at the East
London site has been dedicated to the manufacture of core,
low-volume pharmaceutical products. A capital expenditure
project has been initiated to refurbish the relevant manufacturing
areas to install new equipment which will meet existing
demands and also to accommodate future growth. This project
is envisaged to be completed in 2010.
THE STERILE FACILITY COMMENCES
PRODUCTION OF EYE DROPS
The Sterile Facility extends Aspen’s manufacturing capability
into the specialist manufacturing areas of sterile eye drops,
freeze-dried lyophilised vials and sterile injectables, including
the manufacture of injectable hormones. The multi-product
suite producing eye drops was commercialised in August 2009.
The facility is able to produce in excess of 30 million bottles
per year, with close to 24 million units per annum to be
exported into the United States under the manufacturing
contract for Clear Eyes and Murine with Prestige Brands Inc.
Manufacture of Aspen’s other ophthalmic products will also
be phased into this facility over time.
The Sterile Facility has been constructed and validated in
accordance with international standards.
Trials have been initiated in the injectable suite of the Sterile
Facility. These areas are scheduled to be commercialised
during 2010. Contracts are in place with leading multi-national
pharmaceutical companies Eli Lilly and Bayer for
the manufacture of products for international markets. The
successful validation, commissioning and commercialisation
of this highly specialised and sophisticated plant is testament
to the efforts, skills and competence of the management and
staff involved in the project.
CAPACITY ENHANCEMENTS AT THE
NUTRITIONALS FACILITY
As a result of growing demand, a project is underway to increase
the blending capacity by more than 50% at the Nutritionals
Facility in Johannesburg. Following completion of this project in
October 2009, this facility will be positioned to meet local and
international demand.
An explosion, induced by the combustion of dust particles,
occurred in the drying tower on 18 August 2009. The explosion
and resultant fire caused extensive damage to this part of the
facility.
However, production in the blending and packing areas
remains uninterrupted. It is expected that the drying tower
will recommence production in the second half of 2010.
A contingency plan, utilising outsourced production, has
been implemented to ensure continued supply of IMFs into
the market. Aspen is fully insured against damage and loss of
profits arising out of this incident.
CONTINUOUS IMPROVEMENT PROJECTS
ENHANCE EFFICIENCIES
A number of continuous improvement projects have been
implemented successfully across the South African facilities
with a committed objective to increase efficiency and reduce
costs. Continuous improvement targets are set and monitored
periodically to measure progress. Achievements recorded to
date include:
- The doubling of batch sizes to reduce set-up time between
batches and thereby optimise equipment utilisation;
- Enhancement of cleaning validation studies to improve set-up
times;
- Elimination of redundant in-process tests to improve
throughput times;
- Automation of end-of-line packing to match the increased
rate of manufactured output; and
- Improvement of product yields through manufacturing
process improvements and advanced training of operators.
To implement and embed the improved manufacturing
technologies and processes, a committed investment has been
made in the training and development of all operating and support
staff throughout the facilities. Accelerated skills development,
on-the-job coaching and ongoing GMP training have contributed
to the achievement of continuous improvement objectives. |