
Safety
As reported in FY10, an explosion underground shortly after year end tragically resulted in five fatalities (FY10: three). There were no further fatalities in the review period. The LTIFR for FY11 was 10.27 per million hours worked (FY10: 8.40).
 |
More detailed information on safety performance and Harmony’s sustainable development concerns in South Africa can be found in the online sustainable development report with a summary on pages 6 to 15 of this report. |
Phakisa employed 3 105 people in FY11, including 239 contractors.
 |
Detailed information on Phakisa’s resources and reserves appears in the mineral resources and mineral reserves section of this annual report. |
Operations review
Milled volumes increased by 14% year on year. This, together with a 13% improvement in recovered grade mined, contributed to a 29% increase in gold produced to 56 649oz as part of the build-up strategy.
The start of the review period was tragically marred for Phakisa after an explosion, caused by an underground fire, in which five mine rescue team members died while manning a fresh-air base. This event also resulted in the loss of 13 production days, exacerbated by an ice-pipe failure in the shaft and fire in the 66 – 63 stope.
The production build-up was affected by geological issues, illegal mining activities and down-time on the new infrastructure. Pleasingly, Phakisa set a record of 1 763t ice per day, resulting in water temperatures of <6°C which in turn improved both ventilation and productivity. Some remaining issues with the ice plant as well as settler failure at Nyala are being addressed.

Phakisa key statistics
| Production |
|
FY11 |
FY10 |
FY09 |
| Volumes milled |
000t (metric) |
387 |
339 |
185 |
| |
000t (imperial) |
427 |
374 |
204 |
| Gold produced |
kg |
1 762 |
1 371 |
691 |
| |
oz |
56 649 |
44 079 |
22 216 |
| Average grade |
g/t |
4.55 |
4.04 |
3.74 |
| |
oz/t |
0.133 |
0.118 |
0.109 |
| Financial |
|
|
|
|
| Revenue |
R million |
551 |
375 |
171 |
| |
US$ million |
79 |
50 |
19 |
| Operating cost* |
R/kg |
269 531 |
232 190 |
160 712 |
| |
US$/oz |
1 200 |
953 |
555 |
| Operating profit |
R million |
78 |
49 |
64 |
| |
US$ million |
11 |
7 |
7 |
| Capital expenditure |
R million |
369 |
486 |
461 |
| |
US$ million |
53 |
64 |
51 |
| People |
|
|
|
|
| Number of employees |
|
|
|
|
| Employees |
|
2 866 |
2 858 |
|
| Contractors |
|
239 |
176 |
|
| Total |
|
3 105 |
3 034 |
|
| HDSAs in management |
% |
30 |
32 |
|
| Women in mining |
% |
9 |
11 |
|
| Training and development expenditure |
R million |
14 |
10 |
|
| Safety |
|
|
|
|
| Fatalities |
|
5 |
3 |
|
| LTIFR |
per million hours worked |
10.27 |
8.40 |
|
| Environment |
|
|
|
|
| Electricity used |
000MWh |
95 |
67 |
|
| Water used for primary activities** |
000m3 |
717 |
408 |
|
| GHG emissions |
000t CO2e |
247 |
81 |
|
| Expenditure on local economic development |
R million |
5 |
2 |
|
| Status of mining right |
New-order mining right granted in December 2007 |
|
| * Includes royalty payment in FY10 and FY11. |
| ** Increase primarily relects transition from development phase to production. |
Equipment salvaged from the closed Merriespruit 1 shaft early in the period reduced the need for capital spent on equipment. Most of phase 1 infrastructure was completed before the interim stage and modifications to loading boxes on 77 level by the new year.
Since it is still a new mine, development at Phakisa is currently centred close to the shaft in the lower-grade areas. The major drive is on developing the area to the north to access higher-grade zones and move closer to the average reserve grade. Grades will improve further as development progresses towards the north and more reef is exposed in the major north-west to south-east trending Basal Reef payshoot.
Financial review
Revenue for the year rose by 47% to R551 million, boosted by the increase in production and higher gold price received. In dollar terms, revenue was up 58% to US$79 million. Costs increased as a result of production build-up costs and the cost of employees transferred from closed shafts to Phakisa. With the transition from project phase into production, a portion of Phakisa’s commissioning costs were capitalised. Cash operating costs in rands increased by 16% to R269 531/kg and were 26% up in dollar terms to US$1 200/oz.
Capital expenditure for the year was R369 million (US$53 million), the bulk of which was spent on the expansion project as well as ongoing development and maintenance of major equipment.

|