Build-up operations

 
 
 
 


View download options
 
Kusasalethu
   
Kusasalethu mine, on the Gauteng/North West border, comprises twin vertical and twin sub-vertical shaft systems. Mining is via conventional methods in a sequential grid layout. Ore mined is treated at the Kusasalethu plant.
 

 

Safety

The focus on creating a safe working environment at Kusasalethu continued to add value, with the mine recording one million fatality-free shifts during the year. Regrettably there were two fatalities after this achievement (FY10: two, FY09: five). The LTIFR regressed to 7.74 per million hours worked (FY10: 6.88).

Seismicity remains a risk and management continues to focus on improving the quality of pre-conditioning at the stope face to reduce the risk presented by small, but damaging, seismic events.

More detailed information on safety performance and Harmony’s sustainable development concerns in South Africa can be found in the online sustainable development report with a summary on pages 6 to 15 of this report.

Kusasalethu employed 5 756 people (including 773 contractors) in FY11.

Detailed information on Kusasalethu’s resources and reserves appears in the mineral resources and reserves section of this annual report.

 

Operations review

Volumes milled rose by 6% to just over 1Mt, and gold produced by 3% to 180 334oz, despite a 3% decline in grade in FY11 to 5.10g/t. Currently, 70% of production at Kusasalethu is from production areas below 100 level (the new mine expansion project) and 30% from production areas in the old mine, above 100 level.

Planned build-up at Kusasalethu was hampered by an accident that caused one fatality, damaged the hoisting shaft and therefore constrained hoisting ore to surface.

The largely completed deepening project has extended the sub-vertical shafts, accessing the Ventersdorp Contact Reef up to 3 388 metres below collar. Remaining project work is focused on extending the service shaft to 113 level, completing the refrigeration complex at 100 level and commissioning the 92 level turbine complex.

Kusasalethu key statistics

Production     FY11   FY10   FY09  
Volumes milled   000t (metric)  1 099   1 035   962  
  000t (imperial)  1 212   1 141   1 061  
Gold produced   kg   5 609   5 444   5 422  
  oz   180 334   175 029   174 321  
Average grade   g/t   5.10   5.26   5.64  
  oz/t   0.149   0.153   0.164  
Financial          
Revenue   R million   1 774   1 392   1 422  
  US$ million   254   184   158  
Operating cost*   R/kg   226 398   208 864   191 097  
  US$/oz   1 008   857   660  
Operating profit   R million   453   301   366  
  US$ million   65   40   41  
Capital expenditure   R million   380   430   422  
  US$ million   54   57   47  
People          
Number of employees          
Employees     4 983   5 049    
Contractors     773   636    
Total     5 756   5 685    
HDSAs in management   %   40   33    
Women in mining   %   10   10    
Training and development expenditure   R million   35   39    
Safety          
Fatalities      2   2    
LTIFR   per million hours worked   7.74   6.68    
Environment          
Electricity used   000MWh   663   629    
Water used for primary activities   000m3   2 497   2 138    
GHG emissions   000t CO2e   683   765    
Expenditure on local economic development   R million   5   10    
Status of mining right   New-order mining right granted in December 2007    

* Includes royalty payment in FY10 and FY11.

In terms of grades, Kusasalethu has now reached an area of localised enrichment although the higher grade was diluted by waste being hoisted with reef and delivered to the plant. A decision to rehabilitate the shaft orepass system after major scaling took place inside these excavations resulted in only one orepass system being available for production. Estimates are that the rehabilitation work will take around two years to complete.

The sub-station for the 100-level refrigeration complex and 98-level complex was commissioned early in the year, and mechanical construction work on the refrigeration plants was completed by year end. Sinking was completed to 113 level from 109 level during the year. The mechanical installation of the turbine on 92 level was completed in March 2011.

Other engineering initiatives include greater use of thermal scanning to detect potential ‘hot connections’ on electrical panels, protection relays to prevent power outages and a central monitoring system for all pumps. Rotational dam cleaning has eliminated the risk of silting, which has compromised dam capacity in the past and constrained pumping. Additional instrumentation has been installed on all large dams to monitor their levels and prevent mud from being drawn into the valves, causing production delays.

These and other initiatives are expected to improve productivity.

Financial review

Revenue and cash operating profit increased as a result of the higher average gold price and increase in ounces sold. Revenue was R1 774 million (US$254 million), up 27%. Cash operating profit rose by 50% to R453 million (US$65 million). The cash operating cost increased 8% to R226 398/kg (US$1 008/oz), mainly after annual labour increases and higher electricity tariffs.

Capital expenditure for the year totalled R380 million (US$54 million), mostly for ongoing development (R267 million, US$38 million), maintaining equipment and shaft capital (R63 million, US$9 million) and developing the new mine project (R50 million, US$7 million).

 
    back to top