This is an overview of performance against the key performance indicators in Eskom’s shareholder compact1 with government, which is done at an Eskom company level. (See here for more detailed information on the shareholder compact.)
| Key performance area | Key performance indicator | Target 2011 |
Achieved 2011 |
Achieved 2010 |
Achieved 2009 |
|||
| Provide adequate future electricity for South Africa | Generation capacity installed (Megawatts) | 625 | 315RA | 452RA | 1 770RA | |||
| Transmission lines installed (kilometres of line) | 446 | 443RA | 600RA | 418RA | ||||
| Transmission MVA installed | 3 565 | 5 940RA | 1 630RA | 1 255RA | ||||
| Ensuring reliability of supply of electricity to all South Africans | National load shedding (Generation Induced) or Un-served energy (system minutes) | No load shedding |
NoneRA | NoneRA | 641,5 | |||
| DSM energy efficiency annualised (GWh) | 994 | 1 339RA | n/a2 | n/a2 | ||||
| Ensuring business sustainability of Eskom | Cost of electricity – (rand/MWh) (before embedded derivatives and depreciation) | 327.28 | 296.36RA | 255.09RA | 237.293 | |||
| Internal energy efficiency – annualised current year savings (GWh) | 24.0 | 26.2RA | n/a4 | n/a | ||||
| Water usage (L/kWh sent out) | 1.35 | 1.35RA | 1.34RA | 1.35RA | ||||
| Debt:equity ratio (company) | 2.5 | 1.67RA | 1.69RA3 | 1.323 | ||||
| Interest cover (company) | 1.0 | 1.48RA | 0.72RA3 | (4.72)3 | ||||
| Supporting the developmental objectives of South Africa | Percentage of local content in new-build projects | 50.0% | 79.7RA | 73.9RA | n/a | |||
| Skills development: | ||||||||
| Eskom trainees/bursars (learner pipeline) | 4 500 | 5 283RA | 5 255RA | 5 907 | ||||
| Engineering trainees/apprentices | 3 500 | 4 240RA | 3 780RA | 3 535 | ||||
| Additional number of non-Eskom learners on Eskom-sponsored learning | 450 | 550RA | 236RA | n/a | ||||
| 1. | The compact measures the performance of the electricity business. |
| 2. | The basis of measurement changed for the current year. In prior years, verified savings of 372MWRA (2010) and 916MWRA (2009) were achieved. |
| 3. | Restated |
| 4. | Reporting basis has changed from 2010, therefore not comparable to 2011. |
| RA | – Reasonable Assurance provided by the independent assurance provider (Refer here). |
Generation capacity
The 625MW target for capacity installation was not achieved due to ongoing challenges at Grootvlei unit 5 and Komati unit 4. At Grootvlei, there was a super-heater boiler tube leak. At Komati, the front end of the high-pressure rotor shaft sheared, due to an unexpected blow as a result of a turbine failure.
Transmission lines built
The target installation of 446km of transmission lines was missed by a small margin due to outstanding land and rights issues (outstanding approvals and permits); late access to land and unsuccessful land acquisition for servitudes due to landowner resistance; the unavailability of required outages and rain.
The divisional reports that follow contain a full analysis of Eskom’s performance during the year ended 31 March 2011, from a financial, operational, safety and environmental point of view.