Performance against the shareholder compact

This is an overview of performance against the key performance indicators in Eskom’s shareholder compact1 with government, which is done at an Eskom company level. (See here for more detailed information on the shareholder compact.)

  Key performance area     Key performance indicator   Target  
2011  
Achieved  
2011  
Achieved   
2010   
Achieved  
2009  
 
  Provide adequate future electricity for South Africa     Generation capacity installed (Megawatts)  625   315RA 452RA  1 770RA
  Transmission lines installed (kilometres of line)  446   443RA 600RA  418RA
  Transmission MVA installed   3 565   5 940RA 1 630RA  1 255RA
  Ensuring reliability of supply of electricity to all South Africans     National load shedding (Generation Induced) or Un-served energy (system minutes)  No load  
shedding  
NoneRA NoneRA  641,5  
  DSM energy efficiency annualised (GWh)  994   1 339RA n/a2   n/a2  
  Ensuring business sustainability of Eskom     Cost of electricity – (rand/MWh) (before embedded derivatives and depreciation)  327.28   296.36RA 255.09RA  237.293  
  Internal energy efficiency – annualised current year savings (GWh)  24.0   26.2RA n/a4   n/a  
  Water usage (L/kWh sent out)  1.35   1.35RA 1.34RA  1.35RA
  Debt:equity ratio (company)  2.5   1.67RA 1.69RA3 1.323  
  Interest cover (company)  1.0   1.48RA 0.72RA3 (4.72)3 
  Supporting the developmental objectives of South Africa     Percentage of local content in new-build projects   50.0%   79.7RA 73.9RA   n/a  
  Skills development:          
  Eskom trainees/bursars (learner pipeline)  4 500   5 283RA 5 255RA   5 907  
  Engineering trainees/apprentices   3 500   4 240RA 3 780RA   3 535  
  Additional number of non-Eskom learners on Eskom-sponsored learning   450   550RA 236RA  n/a  
   
1. The compact measures the performance of the electricity business.
2. The basis of measurement changed for the current year. In prior years, verified savings of 372MWRA (2010) and 916MWRA (2009) were achieved.
3. Restated
4. Reporting basis has changed from 2010, therefore not comparable to 2011.
RA – Reasonable Assurance provided by the independent assurance provider (Refer here).

 

Generation capacity

The 625MW target for capacity installation was not achieved due to ongoing challenges at Grootvlei unit 5 and Komati unit 4. At Grootvlei, there was a super-heater boiler tube leak. At Komati, the front end of the high-pressure rotor shaft sheared, due to an unexpected blow as a result of a turbine failure.

Transmission lines built

The target installation of 446km of transmission lines was missed by a small margin due to outstanding land and rights issues (outstanding approvals and permits); late access to land and unsuccessful land acquisition for servitudes due to landowner resistance; the unavailability of required outages and rain.

The divisional reports that follow contain a full analysis of Eskom’s performance during the year ended 31 March 2011, from a financial, operational, safety and environmental point of view.